OPERATIONAL EXPERIENCE IN THE NEW CILVA
INSTALLATIONS AT BELGOPROCESS
J. Deckers, P. Luycx, R. Vanbrabant
BELGOPROCESS
M. Detilleux, Ph. Beguin
BELGATOM
ABSTRACT
CILVA is a centralized treatment facility for b and g low-level and a -suspect waste produced in Belgium, based on a 2000 ton supercompaction installation and an incineration plant for solid and liquid radioactive waste, with a capacity of about 100 kg waste per hour.
After a short description of the CILVA facility, a project developed by BELGATOM for ONDRAF/NIRAS, the Belgian nuclear waste management agency, this paper describes the feedback experience after almost four years of operation of this facility operated by BELGOPROCESS.
The following aspects are coveted in the paper.
BELGATOM is a nuclear and consulting engineering company, providing a wide spectrum of nuclear services, among other in radwaste management, in Belgium and abroad.
BELGOPROCESS, a company set up in 1984 at Dessel (Belgium) where a number of nuclear facilities were already installed, is specialized in the processing of radioactive waste. It is a subsidiary company of ONDRAF/NIRAS According to its mission statement, the activities of BELGOPROCESS focus on three areas:
INTRODUCTION
At the end of the eighties, the low level waste treatment facilities located on the BELGOPROCESS site were rather old and could not be adapted or refurbished to provide for a modern management of radioactive waste. Therefore, in 1989, ONDRAF/NIRAS decided to build, on the same site, a new centralized facility, the CILVA facility, using supercompaction, and incineration for primary waste treatment.
BELGATOM performed the conceptual study of the facility in 1989-1990. Then, BELGATOM acted as Architect Engineer for the detailed design, construction and commissioning of the CILVA plant. These tasks mainly covered the preparation of the invitation to tender, the selection of the various contractors for the different functional units (see further) as well as for the civil works, the building ventilation systems and the utilities. These tasks also covered the overall project management, including management of the supply contracts, follow-up of fabrication, co-ordination and supervision of the on-site activities, performing of tests and commissioning activities for the whole facility.
BELGOPROCESS started the plant operation in June 1994 (first radioactive waste supercompaction) and May 1995 (first radioactive waste incineration). The general schedule of completion of the project is shown in Figure 1. The investment in the supply of the different packages listed above was about 1.2 109 BEF (year 1990).
Figure 1. General Schedule of Completion of the Project
THE CENTRALISED TREATMENT CONCEPT
Description of the Waste
The low level nuclear waste to be processed in the CILVA facility is solid b and g waste with a radio nuclide concentration in the collected waste packages generally less than 5 GBq/m3 (1).
The waste annual design quantities considered are the following:
The waste producers prepare the solid waste in primary packings generally placed in 2201 drums (compressible waste) or in 1 m3 stainless steel containers (combustible waste).
The liquid waste is spent oil, .delivered to the facility in special transport containers, and organic and aqueous solutions delivered in 281 polyethylene bottles.
The transport package contact dose rate generally is lower than the authorized limit of 2 mSv/h (200 mrem/h).
Description of the Facility
The facility is represented in a simplified scheme (figure 2). Its main installations include the following:
These traits are briefly described below.
Figure 2. Description of the Facility
Reception, Storage and Distribution Unit
This unit comprises a road transport reception hall, a waste package reception hall and a large storage hall. After administrative formalities, the transport packages are unloaded and presented at reception where controls are performed: dose rate measurement, surface contamination and weight.
After the conformity of the declaration sheet issued by the producer is checked, all transport packages are marked with a bar code to ensure they can be followed up and traced during treatment in the facility.
The transport packages containing solid waste are placed in the storage hall. The liquid waste bottles are stored in separate rooms with specific protection against explosion and fire.
The spent oil transport containers are stored in a separate area. Their content is transferred to a storage tank. When necessary, the waste packages are transferred to the treatment units described hereafter.
Waste Preconditioning Unit
The facility includes a routing and sorting installation as well as a pretreatment installation.
Supercompaction Unit
In this unit, 200 litre drams are compacted by means of a 2000 t hydraulic press. The obtained pellets are then stacked into 400 litre overpack drums where they will later on be immobilized with mortar in the conditioning unit.
The fully automated installation is designed to treat about 6000 drums per year at a rate of 8 drums per hour. The use of an eight-position turntable for accumulation of the produced pellets, coupled with a computer management system, optimizes the filling of the overpacks.
With an upstream storage area for the 200 litre drums to be supercompacted and for the empty 400 litre overpacks as well as with a downstream storage area for the filled overpacks (both areas equipped with roller conveyers), it is possible to organize separate supercompacting campaigns.
Incineration Unit
To size the incineration unit, a yearly capacity of about 280 t of solid combustible waste and 50 t of liquid waste was considered, to be incinerated in maximum 4000 operation hours.
The primary combustion chamber operates in a partial pyrolisis mode, at a temperature between 800°C and 950°C. The secondary chamber, an after-burning and flue gas retention chamber, provide complete burn-out of combustible products while retaining the gases for minimum 2 seconds at a temperature of about 1050°C.
The automatic furnace feeder takes care of the internal bins in which the solid waste packages have been inserted. Biological waste (animal carcasses, etc.) is frozen and stored in refrigerators prior to being manually loaded in the incinerator.
Liquid waste is pumped into the incinerator, either directly from the transport package, or from a tank. The off-gas system ensures the dry cooldown of the combustion gases in a boiler, their filtration and purification through baghouse filters, HEPA f'ilters, a quencher and a scrubber. The purified gases are released after dilution with the release of the building ventilation extraction air.
Ashes at the bottom of the combustion chamber are slowly moved by two screws. Ashes and dust from the boiler and the baghouse filters are collected in 200 litre drums for further supercompaction.
Conditioning Unit
This unit includes an installation for immobilization and embedding and another one for control and inspection of the conditioned waste.
The drums, ready for final disposal, are transported to an intermediate storage building on the same site.
Waste Traceability System
In the Cilva facility, waste traceability is assured by a centralized waste management system that collects information from the different management systems in the treatment units described before. This management is handled by personal computers. Each drum or package is provided with a bar code. Bar code manners, installed at every stage of the treatment operation, identify each package.
With the help of this management system, the operator has a complete overview, at any time, of the progress of the waste packages inside the facility and of their main characteristics.
OVERVIEW OF OPERATIONAL EXPERIENCE
The operator considers that the global performance of the CILVA facility is very satisfactory. The operator's overview of the operational experience for each of the functional units, including problems solved and lessons learned, is given hereafter.
Reception, Storage and Distribution Unit
The following main results were obtained:
Table I. Reception, Storage and Distribution Unit
From operational experience, and as far as radiological protection is concerned, it appears that:
Precompaction
The precompactor was at the beginning licensed only for preparing special b and g -waste (b , g < 4 El0 Bq/m3), which cannot be directly introduced in a drum for supercompaction.
Special care was taken to prevent contamination during the operation of the 140 T precompactor in the cell. Operators wear no special protection clothes or mask, and each special waste item (281-cans, ventilation- and active coal filters) is controlled with respect to surface contamination.
From operational experience it appears that:
These problems were solved by building an additional intervention box where the filters could be introduced in a new plastic bag and, for the 281 cans some adaptations to the filling device of the precompactor were made in order to avoid leakage.
The following main results were obtained:
Table II. Precompaction Performance
The installation is operated during one shift with two operators.
Since no contamination was found around the precompactor or in the working area, BELGOPROCESS decided to use the same infrastructure for treating the a -bearing filters up to an alpha content of 2 E9 Bq/m3. In 1997, the corresponding license was obtained.
As a conclusion we can say that the initially intended performances have been achieved and that the various problems initially experienced during active precompaction were solved in such a way that even a -bearing waste can be treated without the operator having to wear any special protective clothing.
Supercompaction Unit
During the first supercompaction campaign in 1994, only waste with an a content of maximum 4 E7 Bq/m3 was processed. As no contamination spreading took place outside the installation and the contamination of the supercompactor with its turntable was very low, the originally foreseen operational limit for activity was applied. This means that from the beginning of 1995 not only b ,g waste but also a waste, up to 1 El0 Bq/m3, was processed without special measures being taken.
Only after each campaign of a -waste are the supercompactor and its turntable cleaned to prevent a -contamination of the b ,g waste.
From an operational point of view the following problems were encountered:
Table III displays some of the characteristics achieved during the different supercompaction campaigns.
Table III. Comparative Characteristics of Supercompaction Campaigns
The installation is operated in one shift with two operators. The effective throughput was 6.6 drum/hour in 1995, 7.1 drum/hour in 1996 and 7.6 drum/hour in 1997, which are consistent with the design throughput.
As a conclusion, the supercompaction unit has proved that drums with b ,g - waste and with "a - waste" (a content £ 1 El0 Bq/m3) could be treated in a safe way and that the special confinement, connected to the ventilation system of the building, is efficient for collecting aerosols and dust produced during the compaction campaign. The technical performances (Volume Reduction Factor, throughput and intervention time) are satisfying, the VRF has been further optimized by selecting the incoming 2001 drums according to their weight.
Conditioning Unit
The conditioning unit is composed of two installations: one for immobilization of the supercompacted pellets and one for homogeneous embedding of various waste (like sludges, etc.) in a cement matrix. As the latter has not yet been operated due to lack of waste, only the immobilization unit will be discussed.
With the immobilization unit, the following main results were recorded:
Table IV. Conditioning Performance
From an operational point of view, some availability of the system was lost, at the beginning, because the process was fully automated and did not allow for easy manual intervention in case of failure. This problem was solved by introduction of manual sequences in the system.
As a conclusion, the process gives a good qualified product (mechanical compressive strength of grout min. 30 N/mm2) consistent with the ONDRAF/NIRAS specifications for conditioned waste packages ready for final disposal. The daily production capacity has exceeded contractual requirements.
Incinerator Unit
From the active start-up in May 1995 to the end of 1997 the incineration plant has been operated during some 5440 hours and treated 341 ton of solid waste, 65 ton of organic liquid waste and 121 ton of aqueous waste. In particular, during the first year the operation was plagued by various problems.
The main problems were ash screw damage due to erosion and. presence of metallic pieces within the waste, high pressure drop across the bag filters, underpressure control malfunction and failure of the emergency programmable logic controller (PLC). On the other hand we had positive figures for flue gas purification: since the initial start-up, chemical emissions (table V) were much lower than the reference limits and radioactive emissions of typical isotopes such as Co-60 and Cs-137 were below normal detection limits. In 1996, some 140 t of solid waste, 20 t of organic liquids, 53 t of aqueous liquids and 14 t of spent oil were burnt in 1700 hours, leading to an average incineration throughput of 133 kg/h. The radioactivity releases at the stack were only 1.02 E5 Bq in b ,g and 3.7 E3 Bq in a .
Table V. Flue Gas Purification Results
In 1997, 133 ton of solid waste, 23 ton of organic liquids, 59 ton of aqueous liquids and 1 ton of spent oil were burnt in 1738 hours, leading to an average incineration throughput of 127 kg/h.
Capacity figures (table VI) from the beginning to the end of the first operational period illustrate the throughput improvements.
Table VI. Incinerator Capacity and Burn-Out
After the problems were solved it was possible to improve the capacity of the incinerator as follows: for solid waste from 59 kg/h to 79 kg/h and for liquid waste from 35 kg/h to 61 kg/h.
The increase in the capacity of solid waste treatment is mainly achieved through improvements to the fabric filter bags by forming a chalk precoat on the bag fabric and adjusting chalk dosage, while for liquid waste it resulted from a modification of the way the liquid wastes are fed to the combustion chambers.
As we have solved the main problems, we can now focus on improving the bum-out and further increasing the solid waste capacity. However, the present waste quantities to be processed have been significantly reduced following the .waste producers' policy of waste minimization.
While in normal circumstances augers are helpful automatic devices to mix and to transfer the ash to the ash drum, they still remain a delicate component in an hostile environment, they have to be adequately sized and they requite effective precautions to avoid presence of metallic pieces within the waste.
To control the process, a well programmed main PLC coupled with a conventional relay cabinet equipped with indication lamps and switches in the control room is sufficient.
Waste Traceability System
The waste traceability system is operating very satisfactorily for the reception/storage/distribution, the supercompaction and the conditioning units. For the precompactor and incineration units, process signals are also used for traceability purposes, but cause undue interlocking of the waste feed systems of those installations. This problem will be solved by implementing some computer programme adjustment.
GENERAL CONCLUSION
Taking into account the improvements backfitted in recent years, the CILVA plant has reached a state-of-the-art facility status with a high safety standard and a good reliability. Also, it has obtained the ISO 9001 certification. In practice the following were achieved:
Valuable experience and capabilities have been gained performing this project.