MARALINGA REHABILITATION PROJECT

Don Johnson
Thiess Contractors

ABSTRACT

The surface rehabilitation of the former nuclear test sites at Maralinga has created a world benchmark in the cleanup of radioactive materials. Extensive modification of vehicle cabins enabled a well controlled bulk earthworks operation utilising Caterpillar 631 Scrapers to complete the works. The recently completed project was an outstanding success when judged against all key criteria. This paper will deal with the contractor's approach to execution of the project.

INTRODUCTION

The surface rehabilitation of former nuclear test sites at Maralinga was recently completed by Thiess Contractors Pty Limited under a contract with Works Australia (now GHD), the Project Manager appointed by the responsible Australian Government Agency, the Department of Primary Industries and Energy.

The project involved the collection and burial of over 400,000 cubic metres of contaminated soil from over 2,300,000 square metres of arid ground, together with extensive vacuuming and sweeping of rock surfaces, and exhumation of Category 3 burial pits.

This paper will focus on key elements of the Contractor's tendering strategy, and project execution plan.

CONTRACTOR'S PERCEPTION OF CLIENT SELECTION CRITERIA FOR PRE-REGISTERED TENDERS AND THE SUCCESSFUL CONTRACTOR

The client stated in an Information to Tenderers document that "Two streams of management flow through the contract for this project. The first and most important is the management of the radiological risk to health on the site. The second, and subservient, is the management of the construction processes to achieve the Principal's aims with respect to the future safe use of the site".

How did Thiess respond to these stated objectives of the Client?

Firstly, we took a company decision to carry out the project as an internal joint venture between the geographical construction division and the environmental services group, which specialises amongst other things in site remediation. In this manner, we combined specialist remediation knowledge with the necessary skills in bulk earthworks, logistics, industrial relations and safety.

The next challenge was for Thiess to develop a strategy to best respond to the Principal's project requirements. As stated in his tender specification, we were aware that the management of the radiological risk to health on the site was of utmost importance - the key criteria for Contractor selection. However, we knew that other factors would be important considerations in the assessment of the successful tenderer. To this end, we focused on:

As Thiess was successful with its tender, and the project delivery met or bettered all parameters, we can only assume our perception of client selection criteria and key issues on the project was somewhat accurate.

SELECTION OF PLANT AND REHABILITATION METHODS
TO ACHIEVE SPECIFIED CRITERIA

The Contractor was required to select a plant fleet for the project which efficiently collected contaminated soil and debris and met both performance and radiological safety requirements. The specification detailed the following parameters for soil collection plant and equipment

In order to meet the rules in these parameters, the following limitations applied to equipment selection:

Plant fleet options considered by Thiess included:

Our tender was selected based upon the open bowl scraper option. Post tender, we carried out offsite trials to ensure the proposed method would work. At this point, we did change the procedure in that we had originally proposed a grader to windrow the soil (thus providing accuracy in depth control). The windrows were then to be collected via the scraper. We found the type of soil and the head of soil available did not permit reasonable bowl fill factors.

The procedure ultimately utilised on the project involved fitting the scrapers with ultrasound depth detectors and direct cutting the soil by scraper. By managing the haul route and pick up locations of scrapers, no soil recontamination occurred behind the scrapers.

Our total plant fleet included:

MODIFICATION OF PLANT AND EQUIPMENT TO ENSURE SPECIFIED RADIOLOGICAL HEALTH CRITERIA ARE ACHIEVED

The Contractor had a responsibility to design and construct the necessary modifications to plant and equipment to ensure a safe environment existed for operators within a cabin surrounded by a potentially radiologically hazardous environment. The objective was for plant cabins to be radiologically safe, thus avoiding the need for operators to wear personal respiratory equipment.

The criteria that needed to be met for plant modifications included:

Never in our company's history had we faced the challenge posed by the Maralinga project in relation to plant modification requirements.

To achieve these criteria the following processes were adopted. All modifications were designed by Thiess in conjunction with our specialist suppliers and incorporated into a design manual for each item of plant.

After 14 months field operation, the results have demonstrated the suitability of the modifications with zero incidence of cabin pressure failure and no ingress of particles to the operators cabin. Minor problems were encountered early in the project, but these were easily overcome. The most notable of these was cracking of the stainless steel HEPA filter housing.

EXECUTION OF THE WORKS, AND RELATIONSHIP
WITH OTHER PARTIES

The project involved the radiological cleanup of three nuclear test sites - Taranaki, TM 100/101 and Wewak.

The scope of work items involved in the project included:

The following Table I details the breakdown of work at each of the nuclear test sites.

Table I. Key Cleanup Quantities

The total project value at completion was $18.3 million, which represents a cost of $45.70 per metre of contaminated soil collected and buried.

Radiological cleanup criteria, as detailed in the following Table II were achieved or bettered at all locations.

Table II. Cleanup Criteria

TEST SITE

CLEANUP CRITERIA

Taranaki

TM100/101



Wewak

3 KBq/m2

Part - 1.8 kBq/m2
Part - 4.0 kBq/m2

3 kBq/m2

 

The project was executed with all key parameters overwhelmingly successful:

Instrumental to the success of the project was teamwork. We recognised that this project would not be successful by our efforts alone - it needed a committed team approach by Thiess; the Health Physics Provider CH2MHill; and the Client and Project Manager

Partnering was utilised on the project, and whilst I wouldn't like to attribute partnering as being solely successful for the project outcome, it was certainly influential in focusing the team in times of conflict.

The Health Physics regime was critical to the project's success, and to this end we need to single out the efforts of CH2MHill's team. They worked with our employees to provide them with certainty in terms of their safety, and carried out the necessary monitoring of employees such that minimal possible disruption to productive time resulted. Our assumptions at time of tender regarding allowable production time of approximately 6 1/2 hours in a 10 hour day were achieved.

The biggest issue that arose on the project was the interpretation of the water requirement for dust suppression. Achieving the optional position between minimal dust and no mud required trial and error in the harsh climate conditions, and tested the strength of the team's relationship.

The success of the project is no doubt due to the willingness of members of all organisations' staff to co-operate in a strong team environment.

CONCLUSION

The Maralinga Rehabilitation Project will be judged an extremely successful project and a world benchmark in large scale radioactive soil removal.

BACK